Ahtme Elektrijaam — 20 MW Shale Oil Boiler Plant Installation (EPC)

EPC contract for installation of one 10 MW steam boiler and one 10 MW hot water boiler fired by shale oil (LOOS boilers, SAACKE burners).

Project Overview

Turnkey EPC installation for the peak load boiler plant at Ahtme Power Plant. The project involved installing one 10 MW steam boiler and one 10 MW hot water boiler manufactured by LOOS, equipped with SAACKE industrial burners designed for heavy shale oil combustion.

Key Specifications

  • Client: Ahtme Elektrijaam
  • Total Capacity: 20 MW (10 MW steam + 10 MW hot water)
  • Equipment: LOOS boilers, SAACKE burners
  • Fuel: Heavy shale oil