Research and engineering design to upgrade steam capacity for E-25 boilers (#1 & #2).

Project Overview

Comprehensive engineering research, thermal-hydraulic calculations, and design solutions aimed at upgrading and adjusting the nominal steam capacity for E-25 boiler units (#1 and #2) at the Kiviõli Chemical Plant power station.

Key Specifications

  • Client: KIVIÕLI KEEMIATÖÖSTUSE OSAÜHING
  • Equipment: Steam boilers E-25 (#1 & #2)
  • Scope: Engineering research & design solutions